This forum focus on project portfolio risk management theory and RiskyProject Enterprise software. Submit any questions about enterprise risk management, and qualitative / quantitative risk analysis for multiple projects. This forum also includes discussions about project risk analysis on the enterprise level.

Moderator: Intaver Support

Post Reply
Interstate
Posts: 15
Joined: Mon Mar 06, 2006 6:08 pm

Exporting XML to MS Project

Post by Interstate » Sun Nov 04, 2018 11:33 am

Is it recommended to export simulation results back to MS Project?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Exporting XML to MS Project

Post by Intaver Support » Sun Nov 04, 2018 11:37 am

This depends on the objectives for running the analysis? There are a few issues with exporting the results back to MSP that you need to consider:

1. When you open the xml file, if you try import into an existing file, it could overwrite data not directly associated with the simulation results such as custom columns notes etc. We recommend that you import into a new project file rather than an existing one, to avoid the possibility unintentionally of overwriting data.
2. Estimates typically are judgements of the most likely durations ,effort, calendar dates of activities. When you export the results to MSP via xml there is not option to select a risk adjusted most likely. Commonly, users will select , Base results which are the Mean or average for each activity, which will put add an “buffer” to each activity without explicitly stating this.

Because of these issues we recommend caution when exporting results back to MS Project. It can be a useful tool when used correctly, but it should not be performed without first considering why you want the results in MS Project.
Intaver Support Team