Project Risk Score Calculation

This forum focus on project portfolio risk management theory and RiskyProject Enterprise software. Submit any questions about enterprise risk management, and qualitative / quantitative risk analysis for multiple projects. This forum also includes discussions about project risk analysis on the enterprise level.

Moderator: Intaver Support

Post Reply
G&G
Posts: 31
Joined: Tue Mar 07, 2006 3:04 pm
Location: Italy

Project Risk Score Calculation

Post by G&G » Tue May 01, 2018 11:17 am

How is the project risk score calculated?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Project Risk Score Calculation

Post by Intaver Support » Tue May 01, 2018 11:20 am

The “risk” score for the project is a score calculated for either cost or schedule. There are several settings that can be used to calculate the score, however; fundamentally it is calculated:
Risk Score=Results of simulation/original estimate:
  • If the score is < 1 then overall score indicates an opportunity
    If the score is >1 then the score indicates a threat
For calculation of the Score, you can select several options for the results of simulation that include Mean, Mean + Standard Deviation, and other predefined percentiles as the numerator in the formula.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com