Project Risk Score Calculation
Moderator: Intaver Support
Project Risk Score Calculation
How is the project risk score calculated?
-
- Posts: 977
- Joined: Wed Nov 09, 2005 9:55 am
Re: Project Risk Score Calculation
The “risk” score for the project is a score calculated for either cost or schedule. There are several settings that can be used to calculate the score, however; fundamentally it is calculated:
Risk Score=Results of simulation/original estimate:

Risk Score=Results of simulation/original estimate:
- If the score is < 1 then overall score indicates an opportunity
If the score is >1 then the score indicates a threat

Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com