This forum focus on project portfolio risk management theory and RiskyProject Enterprise software. Submit any questions about enterprise risk management, and qualitative / quantitative risk analysis for multiple projects. This forum also includes discussions about project risk analysis on the enterprise level.

Moderator: Intaver Support

Post Reply
NTT
Posts: 24
Joined: Sun May 27, 2007 4:51 pm
Location: Boston, MA

IRR calculation

Post by NTT » Tue Feb 13, 2018 12:59 pm

How is project IRR calculated? What happens with the IRR if project does not have income?
risk manager

bbadmin
Site Admin
Posts: 18
Joined: Tue Nov 08, 2005 8:34 pm

Re: IRR calculation

Post by bbadmin » Tue Feb 13, 2018 1:01 pm

IRR provides a rate (%) of expected return based on the difference between the present value of income and the present value of project costs over the life of the project or a period of time. Net present value uses a discount rate, which generally represents the cost of borrowing (interest) to calculate the current or present value of a project.

Very simply if we have calculated the net present values (discounted) for income and cost, IRR = profit/cost as a %. In the example below, the NPV $249.941 profit represents a 47% IRR. If there is no income, IRR is 0.