Just upgraded to the new version of RiskyProject Enterprise and the probabilities and scores are showing as 1-5 rather than %. How do I change this?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Modifying how probability, impact and scores are displayed
The reason that you are seeing this change is that the default method selected with the new installation is the what we call the Index of the label.
RiskyProject has 5 different display options for probability, impact and scores. These are configured in the Format Risk Matrix dialog box. These display options are located in the bottom left corner of the dialog box.

To change how risk probability and impacts values are displayed to %, click the Show % only option.
RiskyProject has 5 different display options for probability, impact and scores. These are configured in the Format Risk Matrix dialog box. These display options are located in the bottom left corner of the dialog box.

To change how risk probability and impacts values are displayed to %, click the Show % only option.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com