Criticality Index
Moderator: Intaver Support
Criticality Index
How do I see the % of time (across iterations) that a particular task is on the critical path (“% criticiality”)?
-
- Posts: 1008
- Joined: Wed Nov 09, 2005 9:55 am
Re: Criticality Index
1. Turn on the critical path calculation. This will impact performance as CP requires both a forward and backward pass through the schedule. Here is how to do this RiskyProject Help Content (intaver.com)
2. Add the criticality index column to the Result Gantt view.
2. Add the criticality index column to the Result Gantt view.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com