Criticality Index

Posted: Wed Aug 03, 2022 3:20 pm
by RiskGuru
How do I see the % of time (across iterations) that a particular task is on the critical path (“% criticiality”)?

Re: Criticality Index

Posted: Wed Aug 03, 2022 3:23 pm
by Intaver Support
1. Turn on the critical path calculation. This will impact performance as CP requires both a forward and backward pass through the schedule. Here is how to do this RiskyProject Help Content (intaver.com)
2. Add the criticality index column to the Result Gantt view.