Isolating impact of Risk Events and Uncertainties

Posted: Mon Mar 14, 2022 8:02 pm
by Col
Is it possible to quickly separate the effects of uncertainties from risk events?

Re: Isolating impact of Risk Events and Uncertainties

Posted: Mon Mar 14, 2022 8:07 pm
by Intaver Support
To Isolate the impacts of uncertainties you can disable all risks in the Risk ribbon.
Image

To isolate the impact of uncertainties is more difficult. I would recommend making a copy of the file and then in the Project view, select all the activities, right click on the Activity number column (far left) and from the shortcut menu choose Set Low High Duration or Set Low High Cost.
In the dialog box, click the Set Lo, and High duration equal to base.

Image