Isolating impact of Risk Events and Uncertainties

Post by Col » Mon Mar 14, 2022 8:02 pm

Is it possible to quickly separate the effects of uncertainties from risk events?
Business Development Manager

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Isolating impact of Risk Events and Uncertainties

Post by Intaver Support » Mon Mar 14, 2022 8:07 pm

To Isolate the impacts of uncertainties you can disable all risks in the Risk ribbon.
Image

To isolate the impact of uncertainties is more difficult. I would recommend making a copy of the file and then in the Project view, select all the activities, right click on the Activity number column (far left) and from the shortcut menu choose Set Low High Duration or Set Low High Cost.
In the dialog box, click the Set Lo, and High duration equal to base.

Image
Intaver Support Team