Post-mitigation impact calculation

Posted: Fri Jan 28, 2022 9:43 am
by Tomico
I inserted Post-Mitigation Impact for Schedule and Post-Mitigation Impact for Cost in Risk Register. They are read only. How are they calculated?

Re: Post-mitigation impact calculation

Posted: Fri Jan 28, 2022 9:54 am
by Intaver Support
RiskyProject takes post-mitigation probability, impacts and scores shown in Risk Register from Waterfall tab of Risk Information dialog. It is the last line, or last mitigation plan, defined by user. Risk register can also display post-mitigation probabilities, impacts and scores for individual category. They are calculated based on:

- Post mitigation probabilities, impacts and scores for all categories
- Pre mitigation probabilities, impacts and scores for all categories
- Pre mitigation probabilities, impacts and scores for individual categories