Applying Risks to Consolidated Schedules

Post by Tomico » Mon Nov 01, 2021 7:25 pm

Can risks be applied before and/or after a schedule has been consolidated?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Applying Risks to Consolidated Schedules

Post by Intaver Support » Mon Nov 01, 2021 7:35 pm

Risks should be applied after consolidation has been performed. If a risk is applied to a single activity prior to consolidation, it will be assigned with the same probability and impacts to a consolidated task and which may not be optimal.
Intaver Support Team