Applying Risks to Consolidated Schedules

Posted: Mon Nov 01, 2021 7:25 pm
by Tomico
Can risks be applied before and/or after a schedule has been consolidated?

Re: Applying Risks to Consolidated Schedules

Posted: Mon Nov 01, 2021 7:35 pm
by Intaver Support
Risks should be applied after consolidation has been performed. If a risk is applied to a single activity prior to consolidation, it will be assigned with the same probability and impacts to a consolidated task and which may not be optimal.