Modeling Probabilistic Activities in MS Project or RiskyProject

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
NTT
Posts: 24
Joined: Sun May 27, 2007 4:51 pm
Location: Boston, MA

Modeling Probabilistic Activities in MS Project or RiskyProject

Post by NTT » Tue Mar 31, 2020 5:31 pm

We are going to use branching to simulate the impact of additional activities that will occur if we have a failed test. We would like to maintain this model in MS Project rather than RiskyProject. Problem is that it in MS Project this affects the critical path calculation, do you have any suggestions?
risk manager

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Modeling Probabilistic Activities in MS Project or RiskyProject

Post by Intaver Support » Tue Mar 31, 2020 5:39 pm

If you would like to maintain the branching structure in MS Project. We recommend using the Active/Inactive Task feature.

To inactivate a task(s):

Once you have created your schedule in MS Project, select the branch that you do not want to be on the critical path.
On the Tasks tab, click Inactivate. Inactive tasks will appear as "Task Name" (strikethrough) and Gantt bar will be transparent.

Image

When you import the schedule to RiskyProject, the Inactive tasks will appear as normal tasks and you can then model your probabilistic or conditional branching.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com