Managing LOE Tasks

Posted: Mon Dec 02, 2019 3:39 pm
by Jason
Is there any way to handle Hammock activity in Riskyproject?

Re: Managing LOE Tasks

Posted: Mon Dec 02, 2019 3:40 pm
by Intaver Support
For LOE activities, it only matters if you are running resource loaded to calculate costs. If this is the case, you need to run two simulations: the first to assess the overall duration uncertainty covered by the LOE activity, the second to apply this uncertainty to the LOE task.

For example, to calculate the uncertainty for a Project Management LOE task, run one simulation to calculate the Project duration uncertainty. For example, if a 100 day project has an expected duration of 90 (Minimum) to 125 (Maximum), I would add an uncertainty coefficients of .9 – 1.25 to the PM LOE task. We have found this generally works quite well.