Irreducible Risk

Post by G&G » Sun Nov 18, 2018 12:46 pm

What is meant by irreducible risk?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Irreducible Risk

Post by Intaver Support » Sun Nov 18, 2018 12:47 pm

Irreducible risk is sum of the aleatory risk, which is modeled using 3 point estimates for Low, Most Likely, and High for duration and cost, and residual risk that remain due to risk events or epistemic risks that cannot be completely eliminated. Often irreducible and residual risk are considered equivalent terms depending upon definitions used.

The main focus of identifying the irreducible risk is that because it is irreducible, it must be accounted for with cost contingency and schedule margin.
Intaver Support Team
Intaver Institute Inc.