Page 1 of 1

Import Calendar from MS Project

Posted: Thu Oct 19, 2006 1:15 pm
by NormanRW
I found that calendar I imported from MS Project is different in RiskyProject. The shift supposes to start at 8:30 in MS Project, but after import it starts at 8:00 in RiskyProject. As a result my schedule in RiskyProject it a little bit off.

Posted: Mon Oct 30, 2006 11:29 am
by Intaver Support
RiskyProject has a little bit different system to define shifts in the calendar than Microsoft Project. You can define shift started only at the beginning of the hour (8:00 a.m, 9:00 a.m. etc.). If you are bringing calendars with uneven shift times from MS Project to RiskyProject, times in the calendars will be adjusted accordingly. So you may see a slight difference in the project schedule.

Posted: Wed Nov 01, 2006 12:07 pm
by NormanRW
Do you have any other issues with moving data from MSProject to RiskyProject?

Posted: Wed Nov 01, 2006 12:11 pm
by Intaver Support
The only issue is current version of RiskyProject does not support separate calendar for resources. As a result, schedule in MS Project and RiskyProject may be different, if resources use different calendars. We are planning to introduce calendar for resources in RiskyProject 3.

Re: Import Calendar from MS Project

Posted: Thu Aug 13, 2020 12:08 pm
by Intaver Support
RiskyProject now supports resource calendars.