Global risk check box

Posted: Wed Jul 19, 2006 2:51 pm
by Josh
How to use "Apply global risks to the task (see Global Risk View)" checkbox within Task Information?

Posted: Wed Jul 19, 2006 2:58 pm
by Intaver Support
By default all global risks from Global Risk view will be applied to all tasks. If you don't want to apply global risks to the particular task, you can uncheck this box. If the box is unchecked only local risks will be applied to the task.

Re: Global risk check box

Posted: Thu Aug 13, 2020 11:04 am
by Intaver Support
The Global Risk view is no longer supported in current versions of RiskyProject. It has been replaced by the Risk Assignment View which presents all risk assignments (local and global) in a combined view.