Updating file causing short delays

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
G&G
Posts: 31
Joined: Tue Mar 07, 2006 3:04 pm
Location: Italy

Updating file causing short delays

Post by G&G » Fri Feb 09, 2024 10:49 pm

When adding risks or 3pt estimates etc the software seems to freeze briefly. Is there a reason for this?

Intaver Support
Posts: 995
Joined: Wed Nov 09, 2005 9:55 am

Re: Updating file causing short delays

Post by Intaver Support » Fri Feb 09, 2024 10:55 pm

RiskyProject has 2 default calculation settings: Deterministic and Probabilistic. When Probabilistic is selected, RiskyProject has an algorithm in which it monitors the size of the data and available computer resources and if it calculates that it can run it in one second it will run a simulation. If the schedule is approaching this limit the time to run the simulation will approach 1 second and can cause this “freezing” behavior.

If this is an issue, in the Project Options -> Calculations, click the Deterministic calculation of Current Schedule only option.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply