Scatter Plot Percentile Setting

Posted: Mon Aug 02, 2021 12:43 pm
by BusinessDecisions
Is there a way to independently set cost and duration percentiles in the cost vs duration scatter plot (e.g. set cost at 90% and duration at 75%)? It appears both percentiles must be the same when selecting the percentiles line in the chart?

Re: Scatter Plot Percentile Setting

Posted: Mon Aug 02, 2021 12:46 pm
by Intaver Support
The Cost vs Duration Scatter Plot uses a slider to set the P-value for schedule (Cost or Finish Times) and the resulting chance of meeting Cost and Schedule at the selected percentile.

Image