Criticality Index

Posted: Thu Feb 25, 2021 1:37 pm
by Tomico
One of our requirements for analysis is a criticality index. Does RiskyProject support this and where can I find it?

Re: Criticality Index

Posted: Thu Feb 25, 2021 1:43 pm
by Intaver Support
Yes, with the most recent version 7.1, criticality index was added to on the KPIs that can be calculated during Monte Carlo simulations. As calculating the criticality index requires a critical path calculation, critical path calculation must be enabled in the Options > Calculations > Calculate Critical Path.

Image

Nest to view Criticality Index for activities, you need to add the Criticality Index column to a any view that you want to use to report the analysis. To add the column, right-click on a column header and from the shortcut menu, click Insert Column ….

Image

Re: Criticality Index

Posted: Thu Jul 27, 2023 1:04 pm
by Intaver Support
After the column with the criticality index is inserted to the grid, the grid information will be saved in to ALM file. So when you reopen project file this column will be presented. It is also possible to save column layout for all future new projects. It is done using Schedule -> Project Options -> View -> Set Default Column Layout.