Using weather calendar vs risk events for cost analysis

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
ManDell
Posts: 14
Joined: Sat Nov 03, 2007 9:08 pm

Using weather calendar vs risk events for cost analysis

Post by ManDell » Wed Aug 07, 2019 11:15 am

When should I use weather calendars vs risk events?
IT Program Manager

Intaver Support
Posts: 989
Joined: Wed Nov 09, 2005 9:55 am

Re: Using weather calendar vs risk events for cost analysis

Post by Intaver Support » Wed Aug 07, 2019 11:18 am

Weather calendars are specifically designed to model known ranges of weather-related non-working days during the execution of a project. The main effect of using weather calendars when also performing cost analysis of time dependent cost analysis using resource rates is that even though there is a weather related delay, no work is performed and therefore no costs are calculated.

Alternatively, if risk events are used to model weather related delays, this acts to expand the length of effected activities and increases the related time dependent costs. Therefore, we recommend that for time dependent costs, we recommend the use of risk events to model delays due to weather if resources will still be working during the weather related delays.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com