Agile and schedule risk analysis

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
RiskGuru
Posts: 18
Joined: Sat Nov 26, 2005 9:27 pm
Location: Toronto, ON

Agile and schedule risk analysis

Post by RiskGuru » Fri Jan 11, 2019 2:21 pm

Is it possible to model Agile projects in RiskyProject?

Intaver Support
Posts: 989
Joined: Wed Nov 09, 2005 9:55 am

Re: Agile and schedule risk analysis

Post by Intaver Support » Fri Jan 11, 2019 2:24 pm

1. It is possible to model Agile projects in RiskyProject, however it does take some adjustment in the methodology and process.
2. Agile has iterations and storyboards which represent the steps (iterations) and deliverables (storyboards)
3. In RiskyProject you can model iterations as activities. Storyboards can be milestones or Summary Activities depending upon how you want to set the project up.
4. While iterations have set durations (e.g two weeks) that unlike activities do not vary, they can experience issues or obstacles that will prevent certain work being completed in a specific iteration. In Agile , you can model these issues as risk that can delay completion.
5. Using Monte Carlo simulations, you can measure how often iterations will be completed on time and whether issues will require additional iterations to complete the storyboard or project scope.
We have recently published a blog post on the use of RiskyProject in Agile methods which provides more detail on the proposed process:
http://intaver.com/blog-project-managem ... anagement/
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject