Is there a quick way to find tasks?

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
Dwen
Posts: 19
Joined: Sat Jun 05, 2010 5:50 am

Is there a quick way to find tasks?

Post by Dwen » Tue Aug 28, 2018 2:48 pm

I have large schedules and would like to know how I can find specific tasks (i.e if duration or start time is greater than certain value)?

Intaver Support
Posts: 989
Joined: Wed Nov 09, 2005 9:55 am

Re: Is there a quick way to find tasks?

Post by Intaver Support » Tue Aug 28, 2018 2:50 pm

There is a Find feature in RiskyProject located on the Schedules tab of the Ribbon. To find activites that meet specific criteria, open the Find dialog box by click the binoculars icon in the Schedule>Zoom and Find group.

The Find dialog box opens. The find dialog box allows you to search all data by columns and highlight all activities that meet the requirement. For example, if you wanted to find any tasks with a duration of more than 20 days in your current schedule. You could set up the search criteria as shown in the example below. The “tests” that are available will allow you to search for activities on any of the data types supported in RiskyProject.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply