Modifying the number of hours or days make up days, weeks and months.

Post by G&G » Tue May 01, 2018 11:10 am

How can I adjust number of hours per day, days in month, and hours per week?

Intaver Support
Posts: 989
Joined: Wed Nov 09, 2005 9:55 am

Re: Modifying the number of hours or days make up days, weeks and months.

Post by Intaver Support » Tue May 01, 2018 11:12 am

In the Project Options > Calendar tab you can define the number of hours/day, hours/week, and days/month.
To set as default values for all new projects, click the Set as default button.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

G&G
Posts: 31
Joined: Tue Mar 07, 2006 3:04 pm
Location: Italy

Re: Modifying the number of hours or days make up days, weeks and months.

Post by G&G » Tue May 01, 2018 11:14 am

If I use schedule from Microsoft Project, does RiskyProject import this settings from the schedule, created in Microsoft Project?

Intaver Support
Posts: 989
Joined: Wed Nov 09, 2005 9:55 am

Re: Modifying the number of hours or days make up days, weeks and months.

Post by Intaver Support » Tue May 01, 2018 11:14 am

Yes. It does.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com