Maximum task durations affect on the simulation results

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
Dwen
Posts: 19
Joined: Sat Jun 05, 2010 5:50 am

Maximum task durations affect on the simulation results

Post by Dwen » Fri Jan 19, 2018 8:47 am

How does the maximum task duration (see deadline tab) affect the results of Monte Carlo simulations.

Intaver Support
Posts: 989
Joined: Wed Nov 09, 2005 9:55 am

Re: Maximum task durations affect on the simulation results

Post by Intaver Support » Fri Jan 19, 2018 8:58 am

It depends on the action that you select if a deadline is met.

No Actions: displays a deadline indicator but will not affect the results of the simulation

End task: ends the task any time the deadline duration is exceeded, so the simulation results will not show any duration greater than the deadline value set.

Cancel task: cancels the task any time the deadline duration is exceeded and sets the duration of the cancelled task to 0. Success rate is calculated based on the % of iterations that do not exceed the deadline duration.

Image
Intaver Support Team
Intaver Institute Inc.