Risks for resources
Moderator: Intaver Support
Risks for resources
How can I assign risks to resources (e.g. chance that the component does not arrive on time equals 70%)?
Business Development Manager
-
- Posts: 962
- Joined: Wed Nov 09, 2005 9:55 am
You can define local and global risks for both task and resources. To define local risks to resources:
1. Go to resource view
2. Click on resource ID, resource information dialog comes up
3. Go to Risks tab
4. Enter risks
To define global risks:
1. Go to Global risks view
2. Enter risks
3. Assign risk to all resources (use Assign column)
1. Go to resource view
2. Click on resource ID, resource information dialog comes up
3. Go to Risks tab
4. Enter risks
To define global risks:
1. Go to Global risks view
2. Enter risks
3. Assign risk to all resources (use Assign column)
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
-
- Posts: 962
- Joined: Wed Nov 09, 2005 9:55 am
Re: Risks for resources
For example, you have a risk "Software developer is sick". It cases delay on 3 days. Probability is 10%. It is assigned to resource "Software Developer". The resource is assigned to 2 tasks. For task 1 the resource is used on 100%. For task 2 the resource is used on 50%. Assigning risk to resources is essentially assigning risk tasks, where this resource is used. However risk probability will be 10% for task 1 and 5% (10% * 50%) for task 2.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
-
- Posts: 4
- Joined: Tue Feb 28, 2006 7:48 am
- Location: United States
Re: Risks for resources
Can I use drag'n'drop view to assign risk to resources?
-
- Posts: 962
- Joined: Wed Nov 09, 2005 9:55 am
Re: Risks for resources
Yes. You just need to switch radio button at the top of right pane to resources.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com