Assigning a multiday delay to a one day task
Posted: Mon Aug 07, 2023 12:13 pm
I have a risk that that the Site Handover might get delayed even with 2 weeks.
If I want to simulate this/ I can set a relative delay even with 85% probability and 70% percent outcome, but the program considers the duration of the task and not the start date of the task. How can I set up that the program can simulate 1-2 weeks possible delay of 1 day activities? It went up only to 1,7 days.
If I want to simulate this/ I can set a relative delay even with 85% probability and 70% percent outcome, but the program considers the duration of the task and not the start date of the task. How can I set up that the program can simulate 1-2 weeks possible delay of 1 day activities? It went up only to 1,7 days.