Page 1 of 1

Updating Risk Assignments

Posted: Wed Nov 23, 2022 7:24 pm
by kp56
How do you update probability and outcome for a risk that has been assigned to multiple tasks? Is it possible to update these values once or do I need to make the changes for each task?

Re: Updating Risk Assignments

Posted: Wed Nov 23, 2022 7:31 pm
by Intaver Support
There are two methods that we recommend. First is the Risk Assignment view. Here this lists all risk assignments to task or resources. Here probability, impacts, and statistical distributions can be updated for each task individually.

Image

2nd method is potentially quicker if you have a record of all the tasks to which a risk is assigned. This is the Drag N Drop. In this case you would select all of these tasks on the left pane, select the risk and drag it onto the selection. As the risk is already assigned, any changes will be applied as updates to the original probability and impacts.

Image