Resource Leveling

Post by katto1 » Sun Mar 15, 2020 9:35 pm

How can I level resources in RiskyProject?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Resource Leveling

Post by Intaver Support » Sun Mar 15, 2020 9:39 pm

RiskyProject does not support resource leveling. Probabilistic resource leveling would most likely not provide a valid result and in most cases would be technically unfeasible due computer performance and differing leveling algorithms that are used by different scheduling software. This refers to how resources are managed. For example if a resource is the first to start on an activity, during leveling should it be the first to be reallocated or the last? If resource leveling is required, we recommend exporting the results of the simulation to a scheduling software such as MS Project or Primavera P6.

RiskyProject can read data from resource leveled schedules. Here is how to do it:
viewtopic.php?f=4&t=1180&p=2460&hilit=Leveling#p2460
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com