What percentiles from your results should you used for your management baseline?
-
- Posts: 977
- Joined: Wed Nov 09, 2005 9:55 am
Re: Using percentiles to calculate management baselines
If you want to use the results of the simulation to create a risk adjusted baseline that the percentile that you use is really a judgement call. Typically, customers who do use the feature export out the Base results (the average durations for each task) to xml which can then be imported into scheduling tools such as MSP for conventional schedule management.