Maximum task duration
Moderator: Intaver Support
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Maximum task duration
RiskyProject has a define maximum task duration of 7300 days. Keep in mind that it is considered best practice to limit tasks to a maximum of 44 days by the DCMA 14 points inspection. Obviously, there are exceptions, but it is best to break down tasks to the smallest possible discrete activities.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com