Probabilistic and conditional branching

Posted: Sun Nov 27, 2005 6:49 pm
by RiskGuru
I found that you have both probabilistic and conditional branching. Could you explain how it works?

Posted: Sun Nov 27, 2005 6:50 pm
by Intaver Support
Probabilistic branching allows the project to branch from one task to another task or group of tasks as part of the simulation process. For example, depending on results of project elaboration, there is a 40% chance that one project alternative will be selected and a 60% chance that another project alternative will be selected.

Conditional branching allows the project to branch from one task to another task based on certain conditions. For example, if a feature development task takes longer than 2 weeks, this may be require shorter development time for other features. Conditions related to task duration, finish time, and cost can be specified for each task that has successors. RiskyProject checks these if then conditions during simulations.

Re: Probabilistic and conditional branching

Posted: Tue May 26, 2020 10:59 am
by Intaver Support
For more information, please see our blog post http://intaver.com/blog-project-managem ... -projects/.