Probabilistic and conditional branching
Moderator: Intaver Support
Probabilistic and conditional branching
I found that you have both probabilistic and conditional branching. Could you explain how it works?
-
- Posts: 977
- Joined: Wed Nov 09, 2005 9:55 am
Probabilistic branching allows the project to branch from one task to another task or group of tasks as part of the simulation process. For example, depending on results of project elaboration, there is a 40% chance that one project alternative will be selected and a 60% chance that another project alternative will be selected.
Conditional branching allows the project to branch from one task to another task based on certain conditions. For example, if a feature development task takes longer than 2 weeks, this may be require shorter development time for other features. Conditions related to task duration, finish time, and cost can be specified for each task that has successors. RiskyProject checks these if then conditions during simulations.
Conditional branching allows the project to branch from one task to another task based on certain conditions. For example, if a feature development task takes longer than 2 weeks, this may be require shorter development time for other features. Conditions related to task duration, finish time, and cost can be specified for each task that has successors. RiskyProject checks these if then conditions during simulations.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
-
- Posts: 977
- Joined: Wed Nov 09, 2005 9:55 am
Re: Probabilistic and conditional branching
For more information, please see our blog post http://intaver.com/blog-project-managem ... -projects/.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com