Baselines for risk information

Post by Expert » Fri Jan 29, 2016 6:01 am

What is the purpose of the risk in different baselines chart for risk information dialog box.

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Baselines for risk information

Post by Intaver Support » Fri Jan 29, 2016 6:06 am

RiskyProject Professional has the ability to save project plans as different baselines. Not only can these baselines have different schedules, but they can also have different risks or same risks with different probabilities and impacts.

Because of this capability, baselines are normally used to model risk plan scenarios and how they can impact project objectives. It is useful to check efficiencies of mitigation and response plans. The Risk in multiple baselines is used to show risk probability and impact for each scenario (baseline). To view risk in different baselines you need to create baselines in Schedule -> Baselines -> Set.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com