Setting cost and duration uncertainties for multiple tasks

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Intaver Support
Posts: 1008
Joined: Wed Nov 09, 2005 9:55 am

Re: Setting cost and duration uncertainties for multiple tas

Post by Intaver Support »

You may assign statistical distribution for duration and fixed cost for a selected group of tasks:
1. Open the Gantt View.
2. Select a group of tasks.
3. Right-click on a Task ID.
4. Select Set Low/High Duration or Low/High Fixed Cost.
5. Enter fixed values or a coefficient to calculate Low and High duration or cost based on the Base duration or cost.
6. Select a distribution from the drop-down list.
7. Click OK to apply changes.

Low and high durations and/or fixed cost will be automatically calculated. If you already manually entered low and high values for fixed cost and duration, the procedure will overwrite these values.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply