Re: Recommended Practices for integrating resources and schedule risk analysis
While resource loaded schedules and schedule risk analysis are not incompatible, how you approach a risk analysis depends upon your objectives as resource loading can introduce additional complications. Depending upon your objectives this could mean creating a specific schedule for your risk analysi...
- Sat Jun 26, 2021 11:42 am
- Forum: Project Portfolio Risk Management
- Topic: Linking Google Docs to Risks
- Replies: 1
- Views: 10505
Re: Linking Google Docs to Risks
In RiskyProject Enterprise you can attach or link documents to specific risks in the Risk Information > Documents tab. Documents that can be linked to a risk include Google docs. There are 2 methods that you can use to link your Google docs to a risk: directly link to an online document or, creating...
- Sun Jun 06, 2021 12:51 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Accessing raw cost simulation data
- Replies: 1
- Views: 10551
Re: Accessing raw cost simulation data
I am assuming you are referring to the Meters on the Project Summary (or Project Information in the Addin). The calculation used is can be seen by clicking the ? on the bottom right corner of the meters. https://www.intaver.com/images/RP_Forum_ScoreMeter.png The raw cost data can be copied from the ...
- Sun Jun 06, 2021 12:45 pm
- Forum: Project Portfolio Risk Management
- Topic: Schedule Reports that show Uncertainty Bands.
- Replies: 2
- Views: 11488
Re: Schedule Reports that show Uncertainty Bands.
Short answer is no. I was thinking that they could be flagged in a text column and filtered but our Text columns do not support filtering. Workaround might be to use a Text Column to flag activities that use Risk Bands > Export the Schedule the Excel and apply the filter to the target column (Risk B...
- Sun Jun 06, 2021 12:39 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Importing Costs from Excel
- Replies: 1
- Views: 10922
Re: Importing Costs from Excel
Currently, we don't this capability implemented directly. We do integrate with Excel, but where you can import data is limited to: - import risk register with their properties - import probabilities and impact of risks. Excel import is expandable in that we can link to additional fields, we would re...
- Tue May 04, 2021 9:24 pm
- Forum: Project Portfolio Risk Management
- Topic: Analyzing mega schedules
- Replies: 2
- Views: 23703
Re: Analyzing mega schedules
In depends on schedule, particularly on number of repeated activities. We tried this algorithm on very many real life schedules. If schedule is relatively small, for example, less than 1000-1500 activities, in our experience reduction will be 5-10%. Some large schedule contain many repeated activiti...
- Tue May 04, 2021 9:16 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Calculating the Cost of Residual Risk
- Replies: 3
- Views: 14952
Re: Calculating the Cost of Residual Risk
If you have assigned a cost to a mitigation plan and assigned it to a risk this is used only for the post-mitigation calculation and does not affect the simulation results. For example, we create a response plan in the Mitigation/Response view with a Cost of $25000. http://www.intaver.com/images/RP_...
- Tue May 04, 2021 9:10 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Configuring Risk Matrix for Quantitative Risk Analysis
- Replies: 1
- Views: 10671
Re: Configuring Risk Matrix for Quantitative Risk Analysis
The reason for this for qualitative risk analysis standard 5 x 5 risk matrix works well as you are only "placing" the risk onto the matrix using a simple probability x impact with subjective scores (1,2,3,4,5) or labels (very low, low,.. etc), From this you get a simple score e.g 3*5= 15 and the ris...
- Tue Mar 23, 2021 1:00 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Setting Chart defaults
- Replies: 2
- Views: 16432
Re: Setting Chart defaults
Chart defaults for all projects at the same time can be defined in RiskyProject Enterprise. In this case you can setup any portfolio settings, save it in database and these settings will be consistent for all projects.
- Tue Mar 23, 2021 12:55 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Calculating the Cost of Residual Risk
- Replies: 3
- Views: 14952
Re: Calculating the Cost of Residual Risk
In most cases, the “Cost of Residual Risk” is the same as the Potential loss. This may sound odd, but mitigation plans normally only lower the probability of risks as this is the most cost efficient. Experience shows that lowering the impacts of a risk often are normally not cost effective. However,...
- Tue Mar 23, 2021 12:51 pm
- Forum: Project Portfolio Risk Management
- Topic: Cost Before Mitigation Property
- Replies: 1
- Views: 11767
Re: Cost Before Mitigation Property
The most probable cause of this issue is that the “Auto Calculation of Expected Loss” is enabled in the Risk Information > Properties tab. The feature introduced in version 7.1 automatically calculates the expected loss if the risk occurs. The calculation does not include probability. It is useful e...
- Thu Feb 25, 2021 1:51 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Applying level of uncertainty using PERT to entire project
- Replies: 1
- Views: 12003
Re: Applying level of uncertainty using PERT to entire project
PERT analysis is different than Monte Carlo simulation. However, using Triangular statistical distribution is analogous distribution when running simulations. While there are several different ways to apply statistical distributions (uncertainty) to activities here is the quickest way: 1. Select eve...
- Thu Feb 25, 2021 1:43 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Criticality Index
- Replies: 2
- Views: 12575
Re: Criticality Index
Yes, with the most recent version 7.1, criticality index was added to on the KPIs that can be calculated during Monte Carlo simulations. As calculating the criticality index requires a critical path calculation, critical path calculation must be enabled in the Options > Calculations > Calculate Crit...
- Thu Feb 25, 2021 1:39 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Exporting results of analysis to P6
- Replies: 1
- Views: 13230
Re: Exporting results of analysis to P6
The results of the analysis can be exported back to P6 using the XML export. The xml format is in a Microsoft Project format that is supported by P6. Documentation on how to import the MSP xml into p6 can be found here: https://docs.oracle.com/cd/E17266_01/p6help/help/en/helpmain.htm?toc.htm?8010.ht...
- Sun Jan 17, 2021 9:19 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: I'm running 1000 simulations for project in my project schedule
- Replies: 1
- Views: 12190
Re: I'm running 1000 simulations for project in my project schedule
It depends on schedule. In most real life projects 600 - 800 iterations will give very accurate results. Remember that accuracy of analysis should correspond with accuracy of input data. Input probability and outcome of risks as well as uncertainties, defined by statistical distribution of task dura...