- Sun Jan 17, 2021 9:05 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Assigning Uncertainty to Entire Project
- Replies: 1
- Views: 14248
Re: Assigning Uncertainty to Entire Project
Here is the easiest way to assign uncertainties to entire project: 1. Select every task – Click on first task ID and drag down. 2. Right-click on a Task ID to open the shortcut menu. 3. Click on Set Low/High Duration. 4. Enter in the coefficients and select the Statistical Distribution and click OK....
- Sun Jan 17, 2021 8:57 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Schedule Consolidation to optimize large schedules for analysis
- Replies: 1
- Views: 13504
Re: Schedule Consolidation to optimize large schedules for analysis
Schedule Consolidation is a feature included with the release of version 7.1 and is used to create a “consolidated schedule” that is an equivalent project schedule with equal cost and duration and cost but with less activities and therefore can decrease time required to run an analysis. Consolidatio...
- Sun Dec 13, 2020 1:46 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: RiskyProject icons in the status bar
- Replies: 1
- Views: 14635
Re: RiskyProject icons in the status bar
When you try to open file, save file, export, import information, open or save RiskyProject templates, or perform any other operations with files in RiskyProject, RiskyProject launches a separate application called RiskyProjectOpen.exe. This application gets file path and reports it to RiskyProject....
- Sun Dec 13, 2020 1:37 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Modifying the Incident Statistics view color scheme
- Replies: 1
- Views: 15682
Re: Modifying the Incident Statistics view color scheme
By default, the Incidents have the same number of classifications as the Risk Matrix. Yes, if you open the incidents tab, click Classifications. The Incident Classifications Settings dialog box opens. http://www.intaver.com/images/RP_Forum_IncidentColor.png Select the classification that you want to...
- Sun Dec 13, 2020 1:31 pm
- Forum: Project Portfolio Risk Management
- Topic: Enable/Disable Incident Reporting
- Replies: 1
- Views: 15251
Re: Enable/Disable Incident Reporting
The Incidents modules can be disabled in the Portfolio Options. Normally, Incidents are disabled by default, so it maybe that someone accidentally enables them during the install or configuration process. To disable the Incidents module, on the Projects tab, Portfolio Settings group, click Portfolio...
- Mon Nov 16, 2020 7:05 pm
- Forum: Project Portfolio Risk Management
- Topic: RiskyProject Professional vs RiskyProject Enterprise
- Replies: 2
- Views: 44760
Re: RiskyProject Professional vs RiskyProject Enterprise
RiskyProject Professional is best suited or the analysis and management of projects by a single user. RiskyProject Professional is desktop software that provides project risk analysis and management. This includes cost and schedule risk analysis using Monte Carlo simulations. RiskyProject Profession...
- Mon Nov 16, 2020 7:04 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: How RiskyProject Enterprise licensing works?
- Replies: 1
- Views: 14866
Re: How RiskyProject Enterprise licensing works?
RiskyProject Enterprise is a client/server application which requires client and server licensing which are separate as the desktop licenses can work either in standalone mode or as a client connected to the Enterprise Server. The Enterprise Server license does not just allow users to connect to a d...
- Mon Nov 16, 2020 6:23 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Modifying Risk Outcome Distributions
- Replies: 1
- Views: 15884
Re: Modifying Risk Outcome Distributions
On every risk assignment that has a 3 point estimate (low, base, high) you adjust the statistical distribution parameters. 1. Locate the risk assignment in any of the views where they can be edited such as the Task Information > Risks tab, Risk Information > Probabilities and Impacts tab, or the Ris...
- Thu Oct 15, 2020 11:13 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Moving a 7.1 version file to an earlier version
- Replies: 1
- Views: 15293
Re: Moving a 7.1 version file to an earlier version
RiskyProject versions are always backwards compatible, but not forward. So you can open a 7.0 file in 7.1, but not the reverse. This is because the data schemes are different between major versions. Because the underlying data schema is different, we can only offer a partial solution of moving the s...
- Thu Oct 15, 2020 11:09 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: XML export results are not the same in RiskyProject and MSProject
- Replies: 1
- Views: 14393
Re: XML export results are not the same in RiskyProject and MSProject
We have looked at this in a little more detail and the reason is not because of differences in the algorithm, it is because the nature of probabilistic data. In this case, the P85 finish time of the predecessor and start time of the successor are correlated but do not represent a calculated schedule...
- Thu Oct 15, 2020 10:58 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: RiskyProject Licesing
- Replies: 1
- Views: 15190
Re: RiskyProject Licesing
Due to the way the MS installation process and the UAC interact. RiskyProject license are assigned per user account in thee registry under HKEY_CURRENT_USER. RiskyProject can be installed on one computer and accessible from all accounts, as long as each account has a license. If many users logon to ...
- Sun Oct 04, 2020 9:50 pm
- Forum: Project Portfolio Risk Management
- Topic: Integration with Asta PowerProject
- Replies: 2
- Views: 20816
Re: Integration with Asta PowerProject
We have many clients who asked as did we actually tried to performed risk analysis based on schedules created in Asta Powerproject. Yes. We tried many schedules created in Asta and import them to RiskyProject. Asta and RiskyProject are compatible with each other. You can use both XML export from Ast...
- Sun Oct 04, 2020 9:39 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Generating seed numbers using formula fields
- Replies: 1
- Views: 14119
Re: Generating seed numbers using formula fields
Seed values are fundamental to generating the random numbers that are required for the Monte Carlo simulation. They are generated randomly by our system, but once set, the values that are sampled from the statistical distributions during each iteration are deterministic. So, If two task have the sam...
- Sat Sep 19, 2020 12:25 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Probabilistic vs Weather Calendar
- Replies: 4
- Views: 28810
Re: Probabilistic vs Weather Calendar
Weather calendar is more intuitive and should be based on reliable historical data about weather events. Bag weather days are almost universally available from public sources.
- Sat Sep 19, 2020 12:23 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Task Icons
- Replies: 3
- Views: 24453
Re: Task Icons
You cannot disable task icons. They are useful to identify type of task. These icons are also present in risk register, incident register and other views. W