Search found 992 matches

by Intaver Support
Sat Nov 27, 2021 1:22 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: DCMA 14 points assessment
Replies: 1
Views: 11536

Re: DCMA 14 points assessment

Schedule diagnostics is a detailed analysis of project schedule and includes DCMA 14 points risk assignment. Using Schedule diagnostic tool you can: 1. Find issues with your project schedule, which would affect results of risk analysis as well as affect integrity and quality of the schedule. RiskyPr...
by Intaver Support
Sat Nov 27, 2021 1:09 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Report: Risk Assignment
Replies: 1
Views: 10893

Re: Report: Risk Assignment

There are a number of way to print risk assignment report: 1. Using Risk Assignment View under Risks. This view will be available if you have project schedule. In this view you can see all tasks with associated risk assignments. You can go to File -> Print or File -> Export to Excel to print or expo...
by Intaver Support
Mon Nov 01, 2021 7:37 pm
Forum: Project Portfolio Risk Management
Topic: MSP Addin support for project consolidation
Replies: 1
Views: 11157

Re: MSP Addin support for project consolidation

The RiskyProject MSP Addin does not include the schedule consolidation feature. You must import the schedule into the RiskyProject Professional desktop either using the Addin or as an xml file to run the consolidation.
by Intaver Support
Mon Nov 01, 2021 7:35 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Applying Risks to Consolidated Schedules
Replies: 1
Views: 11485

Re: Applying Risks to Consolidated Schedules

Risks should be applied after consolidation has been performed. If a risk is applied to a single activity prior to consolidation, it will be assigned with the same probability and impacts to a consolidated task and which may not be optimal.
by Intaver Support
Mon Nov 01, 2021 7:34 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Outcomes vs Moment of Risk
Replies: 2
Views: 56618

Re: Risk Outcomes vs Moment of Risk

You are looking at the "Moment of Risk", not risk outcomes. The confusion arises because “Statistical Distribution for Risk Outcomes” has not been enable and so you only see a single outcome field rather than Low, First thing you need to do is ensure that the "Enable Statistical Distribution for ris...
by Intaver Support
Mon Sep 13, 2021 8:31 am
Forum: Project Portfolio Risk Management
Topic: Importing Risks from Excel
Replies: 4
Views: 26022

Re: Importing Risks from Excel

Here is another important note. Some our clients ask us if Excel spreadsheet needs to be formatted any specific way to be imported to RiskyProject. The only requirement is Risk Register spreadsheet will need to have each risk as a row and risk properties, including risk names, probability and impact...
by Intaver Support
Mon Sep 13, 2021 8:27 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Compatibility and sharing files between versions causing issues
Replies: 1
Views: 11645

Re: Compatibility and sharing files between versions causing issues

RiskyProject versions are always backwards compatible, but they are not forwards compatible. In practical terms what does this mean. You can open files from older versions, in newer versions (backwards compatibility); however, because the new versions are not just an update, but are new software wit...
by Intaver Support
Mon Sep 13, 2021 8:27 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: actual costs
Replies: 1
Views: 12387

Re: actual costs

If you are not using resources as part of your cost calculations then it is straight forward. As activities are completed, you can update cost either in your management schedule or in RiskyProject in the Income and Cost view. On the other hand, if you are using a resource loaded schedule to calculat...
by Intaver Support
Mon Aug 02, 2021 12:48 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Pert Analysis Toolbar
Replies: 1
Views: 11767

Re: Pert Analysis Toolbar

Microsoft Project implements one the Quantitative Risk Analysis technique PERT (Program Evaluation and Review Technique). The PERT model was developed in 1950s to address uncertainty in the estimation of project parameters. According to classic PERT, expected task duration is calculated as the weigh...
by Intaver Support
Mon Aug 02, 2021 12:46 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Scatter Plot Percentile Setting
Replies: 1
Views: 11306

Re: Scatter Plot Percentile Setting

The Cost vs Duration Scatter Plot uses a slider to set the P-value for schedule (Cost or Finish Times) and the resulting chance of meeting Cost and Schedule at the selected percentile.

Image
by Intaver Support
Mon Aug 02, 2021 12:40 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Weekly Exception Calendars
Replies: 1
Views: 12088

Re: Weekly Exception Calendars

We don't have working weeks exceptions in our calendars in RiskyProject. This would significantly slow Monte Carlo simulations. So all working weeks are the same. We can do exceptions based on individual days and day of week. It is probably possible to use individual day exception and replicate it f...
by Intaver Support
Sat Jun 26, 2021 11:44 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Percent % Complete vs % Work Complete
Replies: 1
Views: 11406

Re: Percent % Complete vs % Work Complete

While % Work Complete is useful for managing project progress, it is not recommended for schedule risk analysis as this setting will add additional complications to the creation of a valid risk model. The main objective of schedule risk analysis is to forecast probabilities for finish times and dura...
by Intaver Support
Sat Jun 26, 2021 11:43 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Recommended Practices for integrating resources and schedule risk analysis
Replies: 1
Views: 11586

Re: Recommended Practices for integrating resources and schedule risk analysis

While resource loaded schedules and schedule risk analysis are not incompatible, how you approach a risk analysis depends upon your objectives as resource loading can introduce additional complications. Depending upon your objectives this could mean creating a specific schedule for your risk analysi...
by Intaver Support
Sat Jun 26, 2021 11:42 am
Forum: Project Portfolio Risk Management
Topic: Linking Google Docs to Risks
Replies: 1
Views: 11697

Re: Linking Google Docs to Risks

In RiskyProject Enterprise you can attach or link documents to specific risks in the Risk Information > Documents tab. Documents that can be linked to a risk include Google docs. There are 2 methods that you can use to link your Google docs to a risk: directly link to an online document or, creating...
by Intaver Support
Sun Jun 06, 2021 12:51 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Accessing raw cost simulation data
Replies: 1
Views: 11661

Re: Accessing raw cost simulation data

I am assuming you are referring to the Meters on the Project Summary (or Project Information in the Addin). The calculation used is can be seen by clicking the ? on the bottom right corner of the meters. https://www.intaver.com/images/RP_Forum_ScoreMeter.png The raw cost data can be copied from the ...