Search found 992 matches

by Intaver Support
Fri Jun 17, 2022 12:21 pm
Forum: Project Portfolio Risk Management
Topic: Edit or modify the Risk Dashboard
Replies: 1
Views: 13813

Re: Edit or modify the Risk Dashboard

To start with an empty dashboard, right click on the dashboard and click Clear Dashboard. https://www.intaver.com/images/RP_Forum_RiskDashboard1.png However, it can be useful to reuse some of the existing elements. In this case, you may want do a comparison between the current dashboard and your tem...
by Intaver Support
Fri Jun 17, 2022 12:13 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Visualizing Multiple Baselines
Replies: 1
Views: 14510

Re: Visualizing Multiple Baselines

The issue is that you can create baselines with and without the results of the analysis. If the results of the simulation are not saved with the baseline, the baseline will not appear as a cumulative probability plot. When you create a baseline, the procedure must be followed exactly to save the res...
by Intaver Support
Tue May 17, 2022 11:26 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Customizing Uncertainty Bands
Replies: 1
Views: 11229

Re: Customizing Uncertainty Bands

You are correct, uncertainty bands to calculate Low, Most Likely, and High durations and costs for activities based on your assessments of the inherent risk that tasks have. The dialog that allows you to modify the uncertainty bands is located on the Risk tab > Distribution group. 1. Click the Uncer...
by Intaver Support
Tue May 17, 2022 11:21 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Large master schedule
Replies: 1
Views: 13939

Re: Large master schedule

Without using a 3rd party tool such as MS Project that support master schedules, you have a couple of options 1. Create simplified models of each project as subtasks in a program schedule. For example each project could be rolled up to level 3 activities. You would then apply risks and uncertainties...
by Intaver Support
Wed May 04, 2022 12:12 pm
Forum: Project Portfolio Risk Management
Topic: RiskyProject Enterprise 7.2
Replies: 0
Views: 18361

RiskyProject Enterprise 7.2

Intaver Institute released new version of RiskyProject Enterprise software. RiskyProject Enterprise 7.2 is a major release which includes the following new features: 1. New Risk Dashboard: present hundreds of different key performance indicators (KPIs) and charts related to your risks with a fully c...
by Intaver Support
Wed May 04, 2022 12:09 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject 7.2 is released
Replies: 0
Views: 19349

RiskyProject 7.2 is released

Intaver Institute released new version of RiskyProject software. RiskyProject 7.2 is a major release which includes the following new features: 1. New Risk Dashboard: present hundreds of different key performance indicators (KPIs) and charts related to your risks with a fully customizable Risk Dashb...
by Intaver Support
Mon Mar 14, 2022 8:07 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Isolating impact of Risk Events and Uncertainties
Replies: 1
Views: 11842

Re: Isolating impact of Risk Events and Uncertainties

To Isolate the impacts of uncertainties you can disable all risks in the Risk ribbon. https://www.intaver.com/images/RP_Forum_RibbonUncertainties.png To isolate the impact of uncertainties is more difficult. I would recommend making a copy of the file and then in the Project view, select all the act...
by Intaver Support
Mon Mar 14, 2022 8:03 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Windows 11 Compatibility
Replies: 1
Views: 12742

Re: Windows 11 Compatibility

Yes, all versions of RiskyProject (Lite, Professional, and Enterprise) are compatible with Windows 11.
by Intaver Support
Fri Jan 28, 2022 9:54 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Post-mitigation impact calculation
Replies: 1
Views: 12722

Re: Post-mitigation impact calculation

RiskyProject takes post-mitigation probability, impacts and scores shown in Risk Register from Waterfall tab of Risk Information dialog. It is the last line, or last mitigation plan, defined by user. Risk register can also display post-mitigation probabilities, impacts and scores for individual cate...
by Intaver Support
Fri Jan 28, 2022 9:48 am
Forum: Project Portfolio Risk Management
Topic: Accessing MS Project Field Mapping
Replies: 1
Views: 11941

Re: Accessing MS Project Field Mapping

There is a similar dialog box in desktop version that is can be found in the File > Import > Map Microsoft Project fields.

Image

Image
by Intaver Support
Fri Jan 28, 2022 9:39 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Risk Matrix Percent ranges show 20000000.0%
Replies: 0
Views: 18365

Risk Matrix Percent ranges show 20000000.0%

Sometimes our users are trying to modify the Risk Matrix, however the '%' seem to be completely off. the percentage is showing like "20000000.0%" which is faulty. This problem occurs due to regional settings for decimal and digit group symbol are the same in the regional settings. This causes the so...
by Intaver Support
Tue Dec 21, 2021 5:01 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Importing Microsoft Project Files
Replies: 1
Views: 12092

Re: Importing Microsoft Project Files

Most commonly this error occurs when users attempt to import a *.mpp file. RiskyProject does not support this format. Files should be saved in xml format to import directly to RiskyProject. Alternatively, you can use the RiskyProject Addin for Microsoft Project (installs automatically) to import dat...
by Intaver Support
Tue Dec 21, 2021 4:59 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Branching and milestones
Replies: 1
Views: 11859

Re: Branching and milestones

Because you are looking at probabilities for the project as a whole, the two activities that are at the end of each branch are not needed. We want to interpret what happens to the last activity, not the results of the two branches individually because they will have unrealistic results by themselves...
by Intaver Support
Tue Dec 21, 2021 4:51 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Setting a statistical distribution for group of tasks
Replies: 2
Views: 14496

Re: Setting a statistical distribution for group of tasks

To quickly change the distribution type, you can use the Set Low/High Duration dialog box. This dialog only updates those values that have been modified in the dialog box. For example if you only change the statistical distribution, no other task data will be modified. To modify the statistical dist...
by Intaver Support
Sat Nov 27, 2021 1:28 pm
Forum: Project Portfolio Risk Management
Topic: Advantages of RiskyProject Enterprise
Replies: 1
Views: 18538

Advantages of RiskyProject Enterprise

he possible impact of risks are rarely isolated to a particular project. While the impacts of financial, resources, suppliers, etc can be assessed at the project level, the same risks often have impacts across multiple projects and programs. This poses several questions. What is the cumulative impac...