Search found 58 matches

by Tomico
Tue May 17, 2022 11:17 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Large master schedule
Replies: 1
Views: 6364

Large master schedule

I manage a program with several large projects. I would like to at a minimum to generate an SRA at the program level. Do you have any advice on how to combine or summarize projects into a single schedule that can be analyzed?
by Tomico
Fri Jan 28, 2022 9:43 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Post-mitigation impact calculation
Replies: 1
Views: 5463

Post-mitigation impact calculation

I inserted Post-Mitigation Impact for Schedule and Post-Mitigation Impact for Cost in Risk Register. They are read only. How are they calculated?
by Tomico
Fri Jan 28, 2022 9:40 am
Forum: Project Portfolio Risk Management
Topic: Accessing MS Project Field Mapping
Replies: 1
Views: 5835

Accessing MS Project Field Mapping

We are having problems getting the Addin to load due to our IT system. As a workaround we are going to import XML files into the desktop. How do we map the MS Project fields if we do not have access to the Addin as shown below?
by Tomico
Mon Nov 01, 2021 7:36 pm
Forum: Project Portfolio Risk Management
Topic: MSP Addin support for project consolidation
Replies: 1
Views: 5121

MSP Addin support for project consolidation

Can I use the MSProject Addin to consolidate a project?
by Tomico
Mon Nov 01, 2021 7:28 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Outcomes vs Moment of Risk
Replies: 1
Views: 5067

Risk Outcomes vs Moment of Risk

We are preparing a model to carry out a first real analysis and we have a question. We are assigning risk to different activities and instead of having low average ang most values we have this: We would like to clarify the meaning of each value: Outcome: Is the impact, in this case a fixed impact of...
by Tomico
Mon Nov 01, 2021 7:25 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Applying Risks to Consolidated Schedules
Replies: 1
Views: 5313

Applying Risks to Consolidated Schedules

Can risks be applied before and/or after a schedule has been consolidated?
by Tomico
Sun Jun 06, 2021 12:36 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Importing Costs from Excel
Replies: 1
Views: 5994

Importing Costs from Excel

Does RiskyProject have any file import capabilities where I could tie data in Excel or other format to MS Project tasks to effectively overwrite the existing resource loading that RiskyProject uses? I have so far found no way to do such an import directly into MS Project, and I've tried several.
by Tomico
Thu Feb 25, 2021 1:37 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Criticality Index
Replies: 1
Views: 7029

Criticality Index

One of our requirements for analysis is a criticality index. Does RiskyProject support this and where can I find it?
by Tomico
Thu Feb 25, 2021 1:37 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Exporting results of analysis to P6
Replies: 1
Views: 8210

Exporting results of analysis to P6

We need to import the Mean results of our analysis back to our Primavera P6 project. Is there a way to do this?
by Tomico
Wed Aug 26, 2020 5:05 pm
Forum: Project Portfolio Risk Management
Topic: RiskyProject Enterprise DB version error
Replies: 1
Views: 9101

RiskyProject Enterprise DB version error

I have used the RiskyProjectDB.exe utility to create a new database and when I logon I am getting the following error: "You may trying to connect to incorrect database". We are currently using version 7.1.
by Tomico
Sun Dec 08, 2019 3:38 pm
Forum: Project Portfolio Risk Management
Topic: Importing Risks from Excel
Replies: 4
Views: 17941

Re: Importing Risks from Excel

Is it possible to import risks to desktop version of RiskyProject professional?
by Tomico
Sat Nov 30, 2019 4:56 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Spikes appearing in histograms
Replies: 1
Views: 11894

Spikes appearing in histograms

Need your insight into “correlation”. I have saw your video tutorial and it is evident that similar risks or different activities or separate risks to single activities can be correlated. What if only single individual risk is affecting the each activity? Results are showing spikes. Any solution?
by Tomico
Thu Aug 29, 2019 3:42 pm
Forum: Project Portfolio Risk Management
Topic: Linking summary tasks
Replies: 1
Views: 12191

Linking summary tasks

Is it correct to link summary tasks?
by Tomico
Thu Aug 29, 2019 3:41 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Calculating work with resource calendars
Replies: 1
Views: 12148

Calculating work with resource calendars

How is work being calculated for resource using resource calendars?
by Tomico
Thu Aug 29, 2019 3:39 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Non Working days and Time Dependent Costs
Replies: 1
Views: 12003

Non Working days and Time Dependent Costs

Can I use weather calendars with non-working days when calculating resource costs?