- Sat Mar 15, 2025 4:52 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Resources for learning RiskyProject
- Replies: 1
- Views: 82850
Resources for learning RiskyProject
I would like to get some advice on the best way for learning how to use RiskyProject. Is the recommended method to read the whole documentations (RiskyProject User Guide)or is there a more in-depth step by step tutorial apart from the ones uploaded on YouTube?
- Wed Jan 15, 2025 2:35 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Pre and Post Mitigation scores after MC Simulation
- Replies: 1
- Views: 51206
Pre and Post Mitigation scores after MC Simulation
I added mitigations to each of my risks, and noticed there are pre-mitigation and post-mitigation tables on the Risk Register view. When I run the Monte Carlo analysis, is it assuming mitigation for only those that have already been met based on mitigation date, or is it assuming all mitigations wil...
- Sat Dec 16, 2023 1:15 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Enterprise License expired
- Replies: 1
- Views: 69204
Enterprise License expired
Getting a message that our license has expired. Can you please provide guidance.
- Mon Jul 03, 2023 5:43 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Pre and Post-Mitigation Simulation Results
- Replies: 1
- Views: 69187
Pre and Post-Mitigation Simulation Results
I ran Monte Carlo analysis with pre-mitigation probability and impact, and I received the results. I can see that without mitigation the project Mechanical completion is due at a date with high probability. I also recorded the mitigation actions which reduced the probability and in some cases the im...
- Wed Nov 23, 2022 7:44 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Scaling risk form
- Replies: 2
- Views: 113759
Scaling risk form
When I double click on Risk ID in Risk Register I could see distorted risk form. All tabs in Risk Information dialog box looks OK. How to fix Risk Form?
- Sat Oct 08, 2022 7:04 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Trial period extension
- Replies: 1
- Views: 77637
Trial period extension
Today I wanted to access RiskyProject, but the trial version expired. I would like to see if it is possible to give me access to the application for another week.
- Sat Oct 08, 2022 7:03 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: License already activated message
- Replies: 1
- Views: 77265
License already activated message
I’m getting the below error message when attempting to use my regular desktop license. How can I fix this?
- Tue May 17, 2022 11:17 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Large master schedule
- Replies: 1
- Views: 81553
Large master schedule
I manage a program with several large projects. I would like to at a minimum to generate an SRA at the program level. Do you have any advice on how to combine or summarize projects into a single schedule that can be analyzed?
- Fri Jan 28, 2022 9:43 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Post-mitigation impact calculation
- Replies: 1
- Views: 79157
Post-mitigation impact calculation
I inserted Post-Mitigation Impact for Schedule and Post-Mitigation Impact for Cost in Risk Register. They are read only. How are they calculated?
- Fri Jan 28, 2022 9:40 am
- Forum: Project Portfolio Risk Management
- Topic: Accessing MS Project Field Mapping
- Replies: 1
- Views: 80006
Accessing MS Project Field Mapping
We are having problems getting the Addin to load due to our IT system. As a workaround we are going to import XML files into the desktop. How do we map the MS Project fields if we do not have access to the Addin as shown below?
- Mon Nov 01, 2021 7:36 pm
- Forum: Project Portfolio Risk Management
- Topic: MSP Addin support for project consolidation
- Replies: 1
- Views: 78869
MSP Addin support for project consolidation
Can I use the MSProject Addin to consolidate a project?
- Mon Nov 01, 2021 7:28 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Risk Outcomes vs Moment of Risk
- Replies: 2
- Views: 148291
Risk Outcomes vs Moment of Risk
We are preparing a model to carry out a first real analysis and we have a question. We are assigning risk to different activities and instead of having low average ang most values we have this: We would like to clarify the meaning of each value: Outcome: Is the impact, in this case a fixed impact of...
- Mon Nov 01, 2021 7:25 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Applying Risks to Consolidated Schedules
- Replies: 1
- Views: 78685
Applying Risks to Consolidated Schedules
Can risks be applied before and/or after a schedule has been consolidated?
- Sun Jun 06, 2021 12:36 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Importing Costs from Excel
- Replies: 1
- Views: 73575
Importing Costs from Excel
Does RiskyProject have any file import capabilities where I could tie data in Excel or other format to MS Project tasks to effectively overwrite the existing resource loading that RiskyProject uses? I have so far found no way to do such an import directly into MS Project, and I've tried several.
- Thu Feb 25, 2021 1:37 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Criticality Index
- Replies: 2
- Views: 91791
Criticality Index
One of our requirements for analysis is a criticality index. Does RiskyProject support this and where can I find it?