Search found 19 matches
- Thu Feb 22, 2018 4:00 pm
- Forum: Project Portfolio Risk Management
- Topic: RiskyProject Enterprise System requirements
- Replies: 1
- Views: 82073
RiskyProject Enterprise System requirements
What are the hardware requirements for RiskyProject Enterprise? Do I need very powerful server? Where are Monte Carlo simulations performed the server or the client?
- Mon Feb 27, 2017 11:49 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Defining uncertainties for lags
- Replies: 3
- Views: 27005
Defining uncertainties for lags
Do you have statistical distributions for lags and how are they defined?
- Mon Feb 27, 2017 11:48 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: What is the difference between risk outcome value and risk outcome type?
- Replies: 1
- Views: 17110
What is the difference between risk outcome value and risk outcome type?
Risk Outcomes and Risk Outcome Types
- Mon Feb 27, 2017 11:44 am
- Forum: Project Portfolio Risk Management
- Topic: Assigning Risks to specific objects in the Portfolio Hierarchy
- Replies: 1
- Views: 18403
Assigning Risks to specific objects in the Portfolio Hierarchy
How to can I assign risks to a specific division of our company in RiskyProject Enterprise?
- Thu Jan 05, 2017 11:29 am
- Forum: Project Portfolio Risk Management
- Topic: Importing RiskyProject files to RiskyProject Enterprise
- Replies: 1
- Views: 17788
Importing RiskyProject files to RiskyProject Enterprise
In RiskyProject Enterprise can we import project from RiskyProject Lite?
- Thu Jan 05, 2017 11:24 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Viewing Project results for Work
- Replies: 3
- Views: 27192
Re: Viewing Project results for Work
I found that chart from my version of RiskyProject is different than on the screen shot. Is it a new version?
- Thu Jan 05, 2017 11:23 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Calculating Expected Costs
- Replies: 1
- Views: 16100
Calculating Expected Costs
How do you calculate an expected value for the cost of a project?
- Fri Nov 04, 2016 2:10 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Define distribution for start time of the task
- Replies: 3
- Views: 26787
Re: Define distribution for start time of the task
How can I see output distributions in RiskyProject Lite?
- Fri Nov 04, 2016 2:09 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Duration units
- Replies: 2
- Views: 23238
Re: Duration units
In Microsoft Project you can define duration units for different tasks individually. I think it is not a good practice. I always use the same settings for all tasks. Therefore RiskyProject's way to handle duration units is quite sufficient for us.
- Fri Nov 04, 2016 2:06 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Import MS Project schedule
- Replies: 2
- Views: 21053
Re: Import MS Project schedule
We work with large integrated schedules created in MS Project and export then to RiskyProject all the time. We don't have any problems with it.
- Fri Nov 04, 2016 2:04 pm
- Forum: Project Portfolio Risk Management
- Topic: Launching Microsoft Project from RiskyProject
- Replies: 1
- Views: 16017
Launching Microsoft Project from RiskyProject
Can I launch Microsoft Project from RiskyProject Enterprise and transfer RiskyProject schedules to it?
- Fri Nov 04, 2016 2:02 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Elapsed duration
- Replies: 1
- Views: 16920
Elapsed duration
We have tasks with elapsed duration in Microsoft Project. How is it handled in RiskyProject?
- Fri Nov 04, 2016 2:01 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: How to disable low/high traingles on the Gantt chart
- Replies: 1
- Views: 18327
How to disable low/high traingles on the Gantt chart
How can I disable triangles depicting low and high estimates of task start and finish times in the Gantt chart within Result Gant View?
- Fri Jul 15, 2016 2:12 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Work units
- Replies: 1
- Views: 18398
Work units
Is it possible to assign risk to work units? If not what is the work around
- Thu Nov 26, 2015 10:13 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Correlating multiple risks
- Replies: 1
- Views: 17043
Correlating multiple risks
Let us assume that we have 3 events (Event 1, Event 2 and Event 3) and we want to correlate Event 1 with Event 3 and Event 2 with Event 3. But we don't want to correlate Event 1 with Event 2. How can that be modelled at RiskyProject? I am asking because when I correlate Event 1 with Event 3, and the...