Search found 8 matches

by remerson risk analysis
Mon Jan 18, 2016 11:27 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Joint confidence level chart
Replies: 1
Views: 9469

Joint confidence level chart

I think the tooltip in Joint Confidence Level chart is incorrect. Duration is 8 times smaller than it supposes to be, however chart itself is correct and all samples are displayed properly.
by remerson risk analysis
Mon Jan 18, 2016 11:12 am
Forum: Project Portfolio Risk Management
Topic: Permission to delete risks
Replies: 1
Views: 9094

Permission to delete risks

We use RiskyProject Enterprise. We need to ensure that we give permission to delete risks only to experienced managers, not to all users. How to do it?
by remerson risk analysis
Tue Nov 03, 2015 4:15 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Risk Chart question
Replies: 1
Views: 9387

Risk Chart question

One of our divisions started using RiskyProject and it seems to provide all the standard monte carlo analysis reports. You also have a risk chart view, it looks interesting but we are not quite sure how we can use it to communicate the results to management.
by remerson risk analysis
Sun Oct 25, 2015 12:29 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Filtering risks that are shown in risk register
Replies: 1
Views: 10378

Filtering risks that are shown in risk register

We would like to be able to show specific risks based upon location or project phase with priority based on risk score from monte carlo risk analysis, is there any way to do this?
by remerson risk analysis
Sun Oct 25, 2015 12:28 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Can you risk resource costs
Replies: 1
Views: 10487

Can you risk resource costs

In the Assign to Tasks or Resources view in the Risk Register, we have added a risks to a resource. One is a schedule risk, but the other involves the cost of the risk. We assigned a fixed cost risk, but do not see any impact from after performing the monte carlo risk analysis. Are we doing somethin...
by remerson risk analysis
Wed Sep 16, 2015 4:03 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Risks Assigned to the Project Schedule
Replies: 1
Views: 8872

Risks Assigned to the Project Schedule

Is there an easy way to quickly view how all project risks are assigned? As part of our project reviews we someway to show and justify our risk assignment.
by remerson risk analysis
Wed Feb 07, 2007 4:06 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk wizard
Replies: 1
Views: 19666

Risk wizard

I would suggest employing "risk wizard" to define risks in RiskyProject. "Risk wizard" can be very good tool to capture information about risks probabilities, moment of risks, etc. You can apply for example "probability wheel" to come up with probabilities. Overall I like your software very much. I ...
by remerson risk analysis
Wed Feb 07, 2007 4:02 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Risk project limitations
Replies: 1
Views: 16918

Risk project limitations

I'm trying to import schedule from Primavera to RiskyProject. The project has around 10000 activities. Can I do so?