Forum: Project Risk Analysis and Project Risk Management Theory
Topic: JCL chart
Replies: 2
Views: 46157

Re: JCL chart

Is it important to know what probabilities shown on each quadrant is essentially a number of dots within this quadrant vs. total number of dots (samples). Each dot represents on Monte Carlo simulations
by Intaver Support
Tue Nov 12, 2024 11:06 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Importing Risk Registers into an existing schedule
Replies: 1
Views: 821

Re: Importing Risk Registers into an existing schedule

Check the file and noticed that there are a lot of global risks many of which are assigned to activities that have local task risks. When you import a risk register there is no task assignments, so by default the risks are set as global. However if the risk is global and local at the same time this ...
by Intaver Support
Tue Nov 12, 2024 11:01 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Minimum VM system requirements
Replies: 0
Views: 901

Minimum VM system requirements

The minimum VM requirements for MC simulations. If you have larger schedules, we would recommend upgrading from the minimum requirements. 1. CPU: At least 4 vCPUs. 2. Memory: A minimum of 16 GB of RAM . 3. Storage: SSD storage with at least 128 GB to ensure fast read/write speeds and adequate space ...
by Intaver Support
Tue Nov 12, 2024 11:00 pm
Forum: Project Portfolio Risk Management
Topic: Issues when running RiskyProject on a Virtual Machine
Replies: 1
Views: 839

Re: Issues when running RiskyProject on a Virtual Machine

There can be three types of issues with virtual machines or any other remote desktop connection: 1. Performance of the virtual machine is insufficient. This is seen when elements of interface don't refresh properly, calculation is very slow, there is a delay in response to keyboard entry or button c...
by Intaver Support
Fri Oct 11, 2024 12:05 pm
Forum: Project Portfolio Risk Management
Topic: Addin Calculation button not working in MSP Addin
Replies: 1
Views: 1457

Re: Addin Calculation button not working in MSP Addin

With the update to the MSP cloud the communication between the addin and the calculation engine appears to be blocked or getting interrupted and the calculation is failing. It is an odd situation, because the Addin doesn't work independently of the desktop software as they share the calculation engi...
by Intaver Support
Fri Oct 11, 2024 12:04 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Licensing Expired notification after upgrading to MS 365
Replies: 1
Views: 1395

Re: Licensing Expired notification after upgrading to MS 365

The issue is that with your new install of the MS 365 the procedure must have deleted the previous license activation and there were no available activations (they had been previously used). We have refreshed the license and it can now be reactivated.
by Intaver Support
Fri Oct 11, 2024 12:00 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Rate increase risks
Replies: 1
Views: 1399

Re: Rate increase risks

From looking at the provided files there are a few issues. First, the Rate Increase risk outcome was assigned to all the resources and globally. This double counts the risk so you must remove the global risk assignment. Second, resources that are Material with a cost /use or Cost Type Resource with ...
by Intaver Support
Fri Sep 06, 2024 2:52 pm
Forum: Project Portfolio Risk Management
Topic: Rate increase risks
Replies: 1
Views: 1990

Re: Rate increase risks

From looking at the provided files there are a few issues. First, the Rate Increase risk outcome was assigned to all the resources and globally. This double counts the risk so you must remove the global risk assignment. Second, resources that are Material with a cost /use or Cost Type Resource with ...
by Intaver Support
Fri Sep 06, 2024 2:52 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Level of Effort Tasks and Cost Risk
Replies: 1
Views: 2392

Re: Level of Effort Tasks and Cost Risk

This what is called hammock or level of effort (LOE) tasks and our scheduling engine doesn't support it. The reason is that they cannot be driver of uncertainty in a schedule. For schedule risk analysis, best practice is to remove them before importing into RiskyProject. For cost analysis, if the LO...
by Intaver Support
Fri Sep 06, 2024 2:16 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Trial period expired prior to evaluation
Replies: 1
Views: 2060

Re: Trial period expired prior to evaluation

You can request an extended evaluation license. Send the request to sales@intaver.com with the following information which is required to generate the license.
• Full name
• Company
• Address
• Phone number
• Email
by Intaver Support
Sat Jul 27, 2024 7:13 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risks assigned globally after importing schedule
Replies: 1
Views: 17214

Re: Risks assigned globally after importing schedule

Here is the explanation with an example I have created a risk register with qualitative assessment. https://www.intaver.com/images/RP_Forum_GlobalRisk.png Now I import an MSP xml file: https://www.intaver.com/images/RP_Forum_GlobalRisk1.png You should see that all of the results are gone. This is be...
by Intaver Support
Sat Jul 27, 2024 7:06 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Updating risks during project execuition due to mitigation efforts
Replies: 1
Views: 18183

Re: Updating risks during project execuition due to mitigation efforts

You are correct. Unlike Response plans which can be both quantitative and qualitative, mitigation plans are qualitative plans and has no effect on the simulation results. Regardless of whether you have mitigation plans or not, you should be reviewing and updated risk probability and/or impacts on a ...
by Intaver Support
Sat Jul 27, 2024 7:04 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Cost of risk is too high
Replies: 1
Views: 17579

Re: Cost of risk is too high

If this is happening when the risk is assigned to a single task, I suspect that the activity has a resource with a rate associated with it as well. When you have a schedule risk assigned to a task with a resource rate this will also generate "time dependent" costs. Here is how this works. ...
by Intaver Support
Sun Jun 09, 2024 6:25 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Updating Risk Assignments
Replies: 2
Views: 24419

Re: Updating Risk Assignments

You can also new Risk Information dialog for risk assignments:
- double click on Task ID in any task view
- go to Risks tab
- update risk assignment, alternatives, probabilities, outcome and moment of risk
by Intaver Support
Mon May 13, 2024 2:48 pm
Forum: Project Portfolio Risk Management
Topic: Can Deadline be used to automatically adjust schedules
Replies: 1
Views: 28326

Re: Can Deadline be used to automatically adjust schedules

With deadlines the results will only show that it fails to meet the deadline. It does not compress the schedule as you would like. Typically, schedule compression or acceleration requires a complete rework of the schedule including adding additional resources, more parallel activities. etc as requir...