Search found 1018 matches
- Thu Feb 06, 2025 7:10 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Entering current risk Probability and Impact
- Replies: 1
- Views: 1321
Re: Entering current risk Probability and Impact
This depends on whether it is a qualitative or quantitative analysis. Qualitative: Easiest method is to use the Probabilities and Outcomes tab in the Risk Information view. Though you can set up the Risk Register view to enter the data there. https://www.intaver.com/images/RP_Forum_RiskAssignDlg1.pn...
- Thu Feb 06, 2025 7:05 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Differences between Mitigation, Mitigation Strategy and Response Plans
- Replies: 1
- Views: 1396
Re: Differences between Mitigation, Mitigation Strategy and Response Plans
One thing to consider is whether you are performing qualitative or quantitative analysis. The risk system and interface changes depending upon which methodology you are using. The Risk System itself is configurable from properties (columns) in the views to risk scoring methods, severity ranking etc....
- Thu Feb 06, 2025 7:00 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Enter Completion Date for a Risk
- Replies: 1
- Views: 1302
Re: Enter Completion Date for a Risk
It can be done using RiskyProject dialog box. To invoke Risk Information go to Risk Form tab. In the Timeline box, edit End Date field. It is also possible to at a Date type property to the Properties and then add that to the Risk Form by clicking the Edit Risk Form Layout button and adding this Com...
- Wed Jan 15, 2025 2:56 pm
- Forum: Project Portfolio Risk Management
- Topic: Qualitative vs Quantitative Probability and Impacts
- Replies: 1
- Views: 6443
Re: Qualitative vs Quantitative Probability and Impacts
Qualitative : Easiest method is to use the Probabilities and Outcomes tab in the Risk Information view. You can also set up the Risk Register view to enter the data, but this requires adding specific columns to the view. https://www.intaver.com/images/RP_Forum_InputRiskProb1.png Quantitative : Once...
- Wed Jan 15, 2025 2:51 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Difference between Mitigation, Mitigation Strategy, and Response Plans
- Replies: 1
- Views: 4781
Re: Difference between Mitigation, Mitigation Strategy, and Response Plans
One thing to consider is whether you are performing qualitative or quantitative analysis. The risk system and interface changes depending upon which methodology you are using. The Risk System itself is configurable from properties (columns) in the views to risk scoring methods, severity ranking etc....
- Wed Jan 15, 2025 2:36 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Pre and Post Mitigation scores after MC Simulation
- Replies: 1
- Views: 5660
Re: Pre and Post Mitigation scores after MC Simulation
I think it is a misunderstanding of what the mitigation planning does. Quantitative modeling of mitigation efforts is a type of scenario analysis. Mitigation plans not part of the quantitative analysis in that they are qualitative - plans reduce the risk. However, to run an analysis on it, you have ...
- Tue Nov 12, 2024 11:09 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: JCL chart
- Replies: 2
- Views: 61859
Re: JCL chart
Is it important to know what probabilities shown on each quadrant is essentially a number of dots within this quadrant vs. total number of dots (samples). Each dot represents on Monte Carlo simulations
- Tue Nov 12, 2024 11:06 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Importing Risk Registers into an existing schedule
- Replies: 1
- Views: 14765
Re: Importing Risk Registers into an existing schedule
Check the file and noticed that there are a lot of global risks many of which are assigned to activities that have local task risks. When you import a risk register there is no task assignments, so by default the risks are set as global. However if the risk is global and local at the same time this ...
- Tue Nov 12, 2024 11:01 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Minimum VM system requirements
- Replies: 0
- Views: 12743
Minimum VM system requirements
The minimum VM requirements for MC simulations. If you have larger schedules, we would recommend upgrading from the minimum requirements. 1. CPU: At least 4 vCPUs. 2. Memory: A minimum of 16 GB of RAM . 3. Storage: SSD storage with at least 128 GB to ensure fast read/write speeds and adequate space ...
- Tue Nov 12, 2024 11:00 pm
- Forum: Project Portfolio Risk Management
- Topic: Issues when running RiskyProject on a Virtual Machine
- Replies: 1
- Views: 11953
Re: Issues when running RiskyProject on a Virtual Machine
There can be three types of issues with virtual machines or any other remote desktop connection: 1. Performance of the virtual machine is insufficient. This is seen when elements of interface don't refresh properly, calculation is very slow, there is a delay in response to keyboard entry or button c...
- Fri Oct 11, 2024 12:05 pm
- Forum: Project Portfolio Risk Management
- Topic: Addin Calculation button not working in MSP Addin
- Replies: 1
- Views: 13010
Re: Addin Calculation button not working in MSP Addin
With the update to the MSP cloud the communication between the addin and the calculation engine appears to be blocked or getting interrupted and the calculation is failing. It is an odd situation, because the Addin doesn't work independently of the desktop software as they share the calculation engi...
- Fri Oct 11, 2024 12:04 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Licensing Expired notification after upgrading to MS 365
- Replies: 1
- Views: 12934
Re: Licensing Expired notification after upgrading to MS 365
The issue is that with your new install of the MS 365 the procedure must have deleted the previous license activation and there were no available activations (they had been previously used). We have refreshed the license and it can now be reactivated.
- Fri Oct 11, 2024 12:00 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Rate increase risks
- Replies: 1
- Views: 13081
Re: Rate increase risks
From looking at the provided files there are a few issues. First, the Rate Increase risk outcome was assigned to all the resources and globally. This double counts the risk so you must remove the global risk assignment. Second, resources that are Material with a cost /use or Cost Type Resource with ...
- Fri Sep 06, 2024 2:52 pm
- Forum: Project Portfolio Risk Management
- Topic: Rate increase risks
- Replies: 1
- Views: 12049
Re: Rate increase risks
From looking at the provided files there are a few issues. First, the Rate Increase risk outcome was assigned to all the resources and globally. This double counts the risk so you must remove the global risk assignment. Second, resources that are Material with a cost /use or Cost Type Resource with ...
- Fri Sep 06, 2024 2:52 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Level of Effort Tasks and Cost Risk
- Replies: 1
- Views: 14680
Re: Level of Effort Tasks and Cost Risk
This what is called hammock or level of effort (LOE) tasks and our scheduling engine doesn't support it. The reason is that they cannot be driver of uncertainty in a schedule. For schedule risk analysis, best practice is to remove them before importing into RiskyProject. For cost analysis, if the LO...