Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risks assigned globally after importing schedule
Replies: 1
Views: 10730

Re: Risks assigned globally after importing schedule

Here is the explanation with an example I have created a risk register with qualitative assessment. https://www.intaver.com/images/RP_Forum_GlobalRisk.png Now I import an MSP xml file: https://www.intaver.com/images/RP_Forum_GlobalRisk1.png You should see that all of the results are gone. This is be...
by Intaver Support
Sat Jul 27, 2024 7:06 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Updating risks during project execuition due to mitigation efforts
Replies: 1
Views: 10996

Re: Updating risks during project execuition due to mitigation efforts

You are correct. Unlike Response plans which can be both quantitative and qualitative, mitigation plans are qualitative plans and has no effect on the simulation results. Regardless of whether you have mitigation plans or not, you should be reviewing and updated risk probability and/or impacts on a ...
by Intaver Support
Sat Jul 27, 2024 7:04 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Cost of risk is too high
Replies: 1
Views: 11050

Re: Cost of risk is too high

If this is happening when the risk is assigned to a single task, I suspect that the activity has a resource with a rate associated with it as well. When you have a schedule risk assigned to a task with a resource rate this will also generate "time dependent" costs. Here is how this works. ...
by Intaver Support
Sun Jun 09, 2024 6:25 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Updating Risk Assignments
Replies: 2
Views: 18952

Re: Updating Risk Assignments

You can also new Risk Information dialog for risk assignments:
- double click on Task ID in any task view
- go to Risks tab
- update risk assignment, alternatives, probabilities, outcome and moment of risk
by Intaver Support
Mon May 13, 2024 2:48 pm
Forum: Project Portfolio Risk Management
Topic: Can Deadline be used to automatically adjust schedules
Replies: 1
Views: 21581

Re: Can Deadline be used to automatically adjust schedules

With deadlines the results will only show that it fails to meet the deadline. It does not compress the schedule as you would like. Typically, schedule compression or acceleration requires a complete rework of the schedule including adding additional resources, more parallel activities. etc as requir...
by Intaver Support
Mon May 13, 2024 2:46 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Calculated risk probability is different that the Input Probability
Replies: 1
Views: 15121

Re: Calculated risk probability is different that the Input Probability

Calculated probability can vary from the input. But normally not by much. The reason is similar to throwing a dice. At each iteration, the risk has a 15% of occurring, so after 1 iteration, the probability will be 0 or 100%, after 2 0,30, or 100%. After 100 iterations, it could occur 15x (ie 15%) bu...
by Intaver Support
Mon May 13, 2024 2:44 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Using resources to model a schedule and cost risk
Replies: 1
Views: 15031

Re: Using resources to model a schedule and cost risk

If you model a schedule risk with resources with rates allocated to the affected tasks. The added costs due to the risk will be part of the analysis. Same as if you apply the risk directly to the resource, however if that resource is assigned to any other tasks, they will be affected as well.
by Intaver Support
Wed Apr 10, 2024 6:04 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Calculated risk probability is different than assigned probability.
Replies: 1
Views: 12015

Re: Calculated risk probability is different than assigned probability.

Calculated probability can vary from the input. But normally not by much. The reason is similar to throwing a dice. At each iteration, the risk has a 15% of occurring, so after 1 iteration, the probability will be 0 or 100%, after 2 throws 0,50, or 100%. After 100 iterations, it could occur 15x (ie ...
by Intaver Support
Wed Apr 10, 2024 6:02 pm
Forum: Project Portfolio Risk Management
Topic: Assigning Risks to Tasks with Resource Costs
Replies: 1
Views: 13297

Re: Assigning Risks to Tasks with Resource Costs

If you model a schedule risk with resources allocated to the affected tasks. The added costs due to the increased time due the risk will be calculated based on the resource rate and will be part of the analysis. You can also model this by you apply the risk directly to the resource, however if that ...
by Intaver Support
Wed Apr 10, 2024 5:59 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Automatically adjusting schedules using Latest Project Deadline
Replies: 1
Views: 13300

Re: Automatically adjusting schedules using Latest Project Deadline

With deadlines the results will only show that it fails to meet the deadline. It does not compress the schedule as you would like. Typically the schedule compression or acceleration requires a complete rework of the schedule including adding additional resources, more parallel activities. etc as req...
by Intaver Support
Wed Mar 20, 2024 10:14 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Copying the Default Risk Properties for Review
Replies: 1
Views: 12752

Re: Copying the Default Risk Properties for Review

They can do this in the Default Properties view selecting all of the properties, and copy using the shortcut menu. This list can then by pasted into a spreadsheet or document for review.

Image
by Intaver Support
Wed Mar 20, 2024 10:10 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Low number of Sensitivity Results
Replies: 1
Views: 11707

Re: Low number of Sensitivity Results

Best Practice: Setting Sensitivity Coefficient Threshold There is a threshold that can be set for viewing sensitivity results, where any results that do not meet the sensitivity coefficient threshold are not show as way to simplify the analysis of schedules. If you many activities with similar level...
by Intaver Support
Wed Mar 20, 2024 10:03 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Sorting Risk Assignments view
Replies: 1
Views: 11111

Re: Sorting Risk Assignments view

The Risk Assignment view doesn't sort and the Risk ID is not one of the data fields available. The Assignment view is listed alphabetically. But the Risk Register you can list Alphabetically as well using the buttons at the top left of the Register view so that they are listed in the same order as R...
by Intaver Support
Fri Feb 09, 2024 11:03 pm
Forum: Project Portfolio Risk Management
Topic: Where is the End User License Agreement
Replies: 1
Views: 13572

Re: Where is the End User License Agreement

We do include the EULA as part of the installation Wizard, which must be accepted prior to installation of the software. An example is shown below. https://www.intaver.com/images/RP_Forum_EULA.png It is also available as part of the installation package. You can also request a copy of the current EU...
by Intaver Support
Fri Feb 09, 2024 10:58 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Low number of iterations
Replies: 1
Views: 12154

Re: Low number of iterations

The number of iterations that will be run is set in the Project Options > Calculations tab. Based on the number of iterations you are seeing, convergence is enabled. Convergence occurs when the simulation results equal the mean and standard deviation values that are defined. To run a higher number o...