Search found 57 matches
- Sat Oct 08, 2022 8:14 pm
- Forum: Project Portfolio Risk Management
- Topic: Sorting and Filtering columns
- Replies: 1
- Views: 7974
Sorting and Filtering columns
I am using a trial version of RiskyProject for doing a risk analysis on a project. I am trying to sort activities by activity codes to assign duration uncertainties but do not see any option to do so in the software. I tried to look for tutorial videos on your website but there is nothing that talks...
- Fri Jun 17, 2022 12:30 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Split Tasks
- Replies: 3
- Views: 21465
Re: Split Tasks
Also duration and work of split task after import to RiskyProject can be incompatible with duration and work in Microsoft Project and other project management software. However Start and Finish Times of all tasks should be the same.
- Tue May 17, 2022 11:23 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Customizing Uncertainty Bands
- Replies: 1
- Views: 8785
Customizing Uncertainty Bands
Just downloaded your software and noticed that when I select a task or tasks and right-click to bring up the context menu, a Duration Bands menu appears that appears to calculate duration ranges based on the coefficients. Is it possible to modify these bands and where can I do this?
- Sun Jun 06, 2021 12:47 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Accessing raw cost simulation data
- Replies: 1
- Views: 9126
Accessing raw cost simulation data
Where I can go to see the calculations behind the “Cost Score” on the “Project Information window”? The cost score I’m getting is twice what the duration score is, which doesn’t make much sense to me, given that the overwhelming driver of cost in my project is labor, and the only uncertainties I hav...
- Sat Sep 19, 2020 12:20 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Task Icons
- Replies: 3
- Views: 19818
Re: Task Icons
Is any way to disable task icons?
- Thu Jan 02, 2020 10:46 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Font Size and Display Settings not supported
- Replies: 1
- Views: 15579
Font Size and Display Settings not supported
When I open the risk information diaglog box, it can only display part of the diaglog.The three buttons of "OK","Cancel" and "Help" cannot display on the screen (looking like the following figure).
- Wed Feb 06, 2019 3:13 pm
- Forum: Project Portfolio Risk Management
- Topic: Assigning risks to Agile projects
- Replies: 1
- Views: 15235
Assigning risks to Agile projects
How would you model risks for Agile storyboards?
- Thu Oct 25, 2018 11:25 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Show Risk IDs
- Replies: 1
- Views: 15332
Show Risk IDs
How do I show the Risk ID by default?
- Mon Aug 13, 2018 3:04 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Activities are converted to Must Start on when imported
- Replies: 1
- Views: 11452
Activities are converted to Must Start on when imported
When I import my schedule using the Addin all of my activities are set to “Must Start On” in RiskyProject, even though they are “ASAP” in Microsoft Project? Is there a reason for this?
- Fri Jul 13, 2018 3:59 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: How do I see which tasks most impact the project success rate
- Replies: 1
- Views: 11387
How do I see which tasks most impact the project success rate
In sensitivity view, can I see what activities affect project success rate?
- Fri Jul 13, 2018 3:55 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: When should I use resource risks?
- Replies: 1
- Views: 15575
When should I use resource risks?
What is the difference between assigning risks to resources rather than activities?
- Tue Jun 26, 2018 3:07 pm
- Forum: Project Portfolio Risk Management
- Topic: Does RiskyProject have contingency planning?
- Replies: 1
- Views: 15868
Does RiskyProject have contingency planning?
Does RiskyProject Enterprise have contingency planning?
- Tue Jun 26, 2018 3:06 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Differences between resource types
- Replies: 2
- Views: 18236
Differences between resource types
What is the difference between cost resources, work resources, and material resources?
- Tue Apr 17, 2018 9:51 am
- Forum: Project Portfolio Risk Management
- Topic: Shared Enterprise Resources
- Replies: 1
- Views: 15847
Shared Enterprise Resources
Does RiskyProject Enterprise allow sharing resources between projects?
- Mon Feb 05, 2018 10:58 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Maximum task duration
- Replies: 1
- Views: 10578
Maximum task duration
What is the maximum task duration?