Search found 19 matches
- Thu Jan 02, 2020 10:54 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Scenario Analysis
- Replies: 1
- Views: 83260
Scenario Analysis
Is there any way to analyze various scenario in one schedule and overlay the output charts to visualize the difference?
- Thu Jan 02, 2020 10:52 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: License already activated message
- Replies: 1
- Views: 82853
License already activated message
A new user is trying to connect to one of those license but gets the error message "this license is already activated."
- Wed Oct 03, 2018 9:46 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Chance of risk on duration unit
- Replies: 1
- Views: 82385
Chance of risk on duration unit
How does selecting Chance is applied to duration unit option work?
- Wed Oct 03, 2018 9:45 am
- Forum: Project Portfolio Risk Management
- Topic: Small project calculations
- Replies: 2
- Views: 94249
Small project calculations
How does the Default Calculation for Small Projects options work?
- Wed Oct 03, 2018 9:44 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Effect of deadlines on simulations
- Replies: 1
- Views: 24095
Effect of deadlines on simulations
Do deadlines affect the results of a simulation?
- Tue Aug 28, 2018 2:48 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Is there a quick way to find tasks?
- Replies: 1
- Views: 24829
Is there a quick way to find tasks?
I have large schedules and would like to know how I can find specific tasks (i.e if duration or start time is greater than certain value)?
- Fri Jan 19, 2018 8:47 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Maximum task durations affect on the simulation results
- Replies: 1
- Views: 23469
Maximum task durations affect on the simulation results
How does the maximum task duration (see deadline tab) affect the results of Monte Carlo simulations.
- Fri Jan 19, 2018 8:47 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Modifying Risk Matrix colors
- Replies: 3
- Views: 40250
Modifying Risk Matrix colors
How can I change colors of risk matrix?
- Fri Jan 19, 2018 8:46 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Comparing Cost of Risk
- Replies: 1
- Views: 25251
Comparing Cost of Risk
I want to calculate the cost of risk impacts. I created two baselines and compared their costs. My question is should I use P10, mean or P90 for such analysis?
- Fri Dec 15, 2017 4:34 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: RiskyProject Dashboards
- Replies: 2
- Views: 95947
RiskyProject Dashboards
Does RiskyProject have a dashboard for main project information?
- Mon Dec 04, 2017 1:20 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Project Summary Charts: Show more details
- Replies: 1
- Views: 19816
Project Summary Charts: Show more details
I like to use the Project Summary view in RiskyProject Enterprise as my main dashboard when reviewing the analysis. I have noticed that the markers that I have set up in the Options don’t appear on the charts in the main page. Is there a way to do this?
- Mon Dec 04, 2017 1:14 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Using with Microsoft Project Server files
- Replies: 1
- Views: 19036
Using with Microsoft Project Server files
I am the admin for Microsoft Project Server and trying to assist an associate with being able to use RiskyProject 6 with Project Server 2010. Does RiskyProject work with MS Project Server and what is required?
- Mon Dec 04, 2017 1:07 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Find the number of iterations per Simulation
- Replies: 1
- Views: 19035
Find the number of iterations per Simulation
Is there a way that I can see how many simulations were performed to reach his convergence… I know my client will be asking about that. How many did it take? Etc.
- Fri May 05, 2017 4:02 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Restore a previous baseline
- Replies: 1
- Views: 16778
Restore a previous baseline
How can I restore previous baseline (baseline which I created before)?
- Thu Aug 04, 2016 10:27 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Entering risk properties
- Replies: 1
- Views: 15895
Entering risk properties
I define custom risk property called "Risk Duration". How can enter value for this risk property?