- Tue Jun 23, 2020 3:03 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Cumulative Probability Plot
- Replies: 1
- Views: 79800
Cumulative Probability Plot
Can the software do a probability analysis for varying probabilities (i.e. P20, P50, P80 etc on the same program).
- Tue Jun 23, 2020 2:57 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Pert Analysis
- Replies: 1
- Views: 78294
Pert Analysis
Can the Software do a PERT analysis on a lengthy construction program, imported from MS Projects.
- Fri May 25, 2018 10:05 am
- Forum: Project Portfolio Risk Management
- Topic: RiskyProject Enterprise language support
- Replies: 1
- Views: 82810
RiskyProject Enterprise language support
Can I enter the schedule and risks on different languages? Can it be saved in the RiskyProject Enterprise database?
- Fri May 25, 2018 10:04 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Accrual Methods
- Replies: 1
- Views: 32746
Accrual Methods
What is the cost or income accrual? How does it calculated?
- Fri May 25, 2018 10:03 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Date formats for Views and Reports
- Replies: 1
- Views: 19104
Date formats for Views and Reports
How can I change date format for Gantt view and all reports?
- Sun Mar 25, 2018 9:39 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Risk score calculation
- Replies: 1
- Views: 26344
Risk score calculation
For the same risk I have different impacts for different categories. How the total impact is calculated? Is it maximum, weighted average, etc.?
- Mon Mar 05, 2018 10:00 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Maximum number of risks
- Replies: 2
- Views: 31591
Maximum number of risks
What is the maximum number of risks in RiskyProject?
- Sat Jan 14, 2017 1:01 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Percent completed for summary tasks
- Replies: 1
- Views: 17780
Percent completed for summary tasks
How risky project calculates percent completed for the summary tasks and complete project if different subtasks have different percent completed?
- Sat Jan 14, 2017 12:34 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Remaining Duration
- Replies: 1
- Views: 19172
Remaining Duration
How Risk Project calculates and reports remaining duration?
- Thu Jan 05, 2017 11:33 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Maximum Project Duration
- Replies: 1
- Views: 18556
Maximum Project Duration
What is the maximum project duration in RiskyProject Settings? How does it affect calculations?
- Tue Nov 15, 2016 2:51 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: What is the difference between variable and fixed costs
- Replies: 1
- Views: 18546
What is the difference between variable and fixed costs
Is there a difference between variable and fixed costs in RiskyProject and how are they entered?
- Tue Nov 15, 2016 2:46 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Viewing Project results for Work
- Replies: 3
- Views: 27193
Viewing Project results for Work
Is it possible to create a chart that shows results for Work (#of hrs or effort) for the entire project?
- Thu Mar 24, 2016 3:25 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Qualitative risk analysis
- Replies: 1
- Views: 16038
Qualitative risk analysis
Are fields in Risk Information Dialog box (cost, trigger, etc.) linked to quantitative risk analysis?
- Thu Feb 04, 2016 1:45 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Database schema in RiskyProject
- Replies: 1
- Views: 19197
Database schema in RiskyProject
We are trying to integrate RiskyProject to our system. Can we read RiskyProject results from RiskyProject Database directly?
- Thu Feb 04, 2016 1:29 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Monte Carlo summary results
- Replies: 1
- Views: 16186
Monte Carlo summary results
When I click on the Gantt bar for the project in RiskyProject Enterprise, I don't see any results in some cases.