Search found 10 matches

by Torelli
Sat Jun 26, 2021 11:36 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Recommended Practices for integrating resources and schedule risk analysis
Replies: 1
Views: 11559

Recommended Practices for integrating resources and schedule risk analysis

We have resource loaded schedules. Are there anything recommended practices for running risk analysis with resource loaded schedules.
by Torelli
Sat Jun 26, 2021 11:34 am
Forum: Project Portfolio Risk Management
Topic: Linking Google Docs to Risks
Replies: 1
Views: 11676

Linking Google Docs to Risks

Most of our project documents are saved on a shard Google drive Is there a way to link these to our risks in RiskyProject?
by Torelli
Tue Mar 31, 2020 5:23 pm
Forum: Project Portfolio Risk Management
Topic: Using Branching to Model Response Plans
Replies: 1
Views: 14209

Using Branching to Model Response Plans

I’m trying to set up a scenario where I have a number of tasks/activities in my schedule that are to be executed only if a risk eventuates. These activities are only in the schedule for the response to a certain risk, if it were to eventuate. It is my understanding that this is the intention of Resp...
by Torelli
Fri Jun 09, 2017 11:03 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Resource rate risks
Replies: 1
Views: 9400

Resource rate risks

Can I assign a risk to rate for resources. For example, rate can increase on 10% due to low availability of resources?
by Torelli
Wed Oct 26, 2016 5:16 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Joint Confidence for Activities
Replies: 1
Views: 11549

Joint Confidence for Activities

Is there anyway to calculate the chance that a milestone will meet both cost and schedule goals?
by Torelli
Tue Nov 03, 2015 4:13 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: default values for low and high durat
Replies: 1
Views: 10516

default values for low and high durat

We have a very large schedule and for first run schedule risk analysis I would like it if I could automatically apply low and high duration estimates based on factors.
by Torelli
Mon Sep 28, 2015 1:51 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Risk assumptions vs. risk objectives
Replies: 1
Views: 9504

Risk assumptions vs. risk objectives

Do you have any specific rules how to define textual risk properties, such as risk assumptions and risk objectives?
by Torelli
Mon Sep 28, 2015 1:48 pm
Forum: Project Portfolio Risk Management
Topic: Filtering Risks
Replies: 1
Views: 9228

Filtering Risks

Is it possible to see risks belonging to one category for entire portfolio in RiskyProject Enterprise?
by Torelli
Mon Aug 14, 2006 11:37 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Tornado Diagram
Replies: 3
Views: 27202

Do you have Tornado Diagram in RiskyProject Lite?
by Torelli
Thu Aug 10, 2006 2:43 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject and other risk management products
Replies: 1
Views: 18726

RiskyProject and other risk management products

Could you please explain the difference between RiskyProject and other project risk management products?